| East Village Case Study |
CSP Detention System Goes Vertical By Mike McGough, P.E., Chief Engineer, NCSPA and Mark McCord, Civil Engineer, Southeast Culvert, Inc. When development of the East Village retail center project began, detention was a major point of debate. This site, just north of Atlanta in Roswell, Ga., is in a highly developed corridor in need of some redevelopment. Haines, Gipson and Associates, the engineer of record, considered several options for the detention during the design process. The original design was a concrete vault, but cost and timing brought other ideas into the arena. Offsite drainage to adjacent ponds, chambered systems, and the concrete vault came with a slew of issues such as cost, footprint size, drainage easements, permitting, and construction time. During a value engineering session with the general contractor, a corrugated steel pipe (CSP) detention system was proposed. As a result of the volume required for storage, the system quickly grew and expanded outside of the useable area for detention, but due to a considerable elevation change to the outfall, the idea of a tiered CSP detention was brought about. When the smoke cleared and all of the numbers were on the table, the tiered CSP was the most feasible. The material cost of the CSP system reduced the initial budget by approximately $200,000, not to mention time and labor costs that were saved by choosing a system that was quick and easy to assemble, while staying within the originally designed footprint. Simply stated by Scott Samuel of Haines, Gipson and Associates “at the end of the day, the pipe system won out in cost and timing.” Structural reinforcement measures were taken to insure that the bottom system maintained its integrity. SEC, Inc. performed Finite Element Analysis of the manifold systems to ensure long-term structural performance under dead and live loadings. Once fabrication was complete SEC, Inc. took on the sizeable task of delivering 3,500 feet of 144” pipe to the job site. The system arrived on time and the contractor spent the next two months installing the pipe in conjunction with a massive retaining wall being constructed next to the tiered system. The detention installation was slowed dramatically due to the close proximity of the wall but total time spent on construction of the system was approximately two weeks. Benefits of CSP Exceed Project Needs An often overlooked advantage of using CSP is the well-documented recycled content in every foot of pipe manufactured, a bonus for LEED certified projects. The combination of strength, flexibility, durability and economics made the CSP detention a difficult product to compete with. Today, construction of East Village is complete and new projects are emerging around it, breathing new life into an area in need of smart development. Thanks to a few progressive thinking engineers and contractors, East Village has a functional and durable detention unlike any other. Mike McGough, P.E., is chief engineer for the National Corrugated Steel Pipe Assn. McGough can be reached by e-mail at This e-mail address is being protected from spambots. You need JavaScript enabled to view it . Mark McCord is civil engineer for Southeast Culvert, Inc. McCord can be reached by e-mail at This e-mail address is being protected from spambots. You need JavaScript enabled to view it . |



























East Village Detention – By the Numbers